Night-Shift Bridge Girder Placement in a Congested City Center
Project Overview: Installation of a pedestrian bridge section over a major 6-lane highway during a scheduled 6-hour road closure.
The Challenge:
Working under artificial lighting with limited space for outrigger extension due to underground utility lines (gas and water).
Engineering Solution:
- Equipment: Liebherr LTM 1250-5.1 equipped with VarioBase®.
- Strategy: Using VarioBase® allowed us to extend the outriggers asymmetrically to avoid high-pressure points over the underground utilities while maintaining maximum lifting capacity.
Technical Specs:
- Girder Length: 35 meters.
- Lift Radius: 22 meters.
- Time Window: 00:00 to 06:00 (Completed at 04:45).